Review timing ranges
Project type
Submittal quality
Corrections expected
| Stage | Estimated days | Notes |
|---|---|---|
| First review | 12-20 | Typical queue + assignment |
| Each correction round | 7-14 | Depends on scope clarity |
| Post-approval issuance | 2-5 | Final checks and fees |
| Total planning range | 28-53 | Update when comments arrive |