What should happen before I submit plans to LADBS?
Confirm zoning feasibility, objective standards, utility assumptions, and ADU scope boundaries before final drawings.
How many correction rounds are normal for LA ADU permits?
One to three rounds are common. Fewer rounds depend on complete notes and city-specific sheet expectations.
Can I overlap plan check tasks with contractor bidding?
Yes. Most teams bid during plan check, then lock final pricing after correction comments are resolved.
What delays issuance most often?
Missing details in structural notes, utility scope conflicts, and unresolved correction comments near approval.
Should I track permit status manually?
Manual checks work, but a weekly status log with date-stamped notes prevents missed actions during review.
When should I order a permit dossier?
Order it when an address has prior permit history, open finals, or unclear scope that could affect your filing strategy.